My Chapter Summaries


I am building Plans #1286.   Click on the BLUE links in the table to read more about the lessons I learned while completing the chapters.

 

Chapter

Title

Status

Hours

  Chapter Title Status Hours

1-3

Education

Complete

40

 

15

Firewall Assembly

Complete

30

4

Bulkheads

Complete

48

 

16

Control Systems

Ongoing

40

5

Fuselage Sides

Complete

62

 

17

Center Console

Ongoing

40

6

Fuselage Assembly

Complete

190

 

18

Canopy

Complete

90

7

Fuselage Exterior

Complete

260

 

19

Wings and Ailerons

Complete

120

8

Shoulder Brace & Seatbelts

Complete

27

 

20

Rudders and Winglets

Ongoing

60

9

Landing Gear and Brake

Almost

100

 

21

Strakes and Fuel Tanks

Ongoing

700

10

Canard Wing

Complete

70

 

22

Electrical Systems

Ongoing

40

11

Elevators

Complete

110

 

23

Engine Installation

Ongoing

300

12

Canard Wing Installation

Complete

40

 

24

Covers and Fairings

Ongoing

40

13

Nose Section

Complete

250

 

25

Finishing

Ongoing

100

14

Main Spar

Redone

200

 

26

Upholstery

Complete

20

 

Total Project Hours to Date:

Unknown about 4000 hours

Percent Airframe Complete:

85%

Percent Project Complete:

60%

Estimated Completion Date:

July 2009