My Chapter Summaries


I am building with Plans #678 bought at Sun N Fun 1998.  I started building in May 1998 and am hopeful for first flight before the Fall of 2006.  Click on the links in the table to read more about the lessons I learned while completing the chapters.

Total Project Hours to Date:

2,604 hours

Percent Airframe Complete:

99%

Percent Project Complete:

81%

Estimated Completion Date:

Fall 2006

   

My building profile (as of November 7, 2005):

I have worked 987 days of the available 2,728 days (36%).

That equates to 0.95 hours per day, 29.0 hrs per month, 348 hours per year.

On the days I do work on the plane, I average 2.64 hours per session.

Chapter

Title

Start

Finish

Hours

  Chapter Title Start Finish Hours
1-3 Education --- --- ---  

15

Firewall Assembly

---

---

---

4

Bulkheads

5/21/98

6/25/98

62

 

16

Control Systems

4/9/01

holding

51

5

Fuselage Sides

6/28/98

7/29/98

66

 

17

Center Console

7/10/03

holding

36

6

Fuselage Assembly

8/8/98

9/11/98

84

 

18

Canopy (Rebuild)

3/2/02

4/2/04

264

7

Fuselage Exterior

9/12/98

10/25/98

57

 

19

Wings and Ailerons

5/29/00

1/02/01

224

8

Shoulder Brace & Seatbelts

10/29/98

11/17/98

71

 

20

Rudders and Winglets

12/17/00

holding

109

9

Landing Gear and Brake

11/21/98

1/25/99

132

 

21

Strakes and Fuel Tanks

8/2/01

3/1/02

213

10

Canard Wing

1/27/99

3/8/99

62

 

22

Electrical Systems

---

---

---

11

Elevators

3/9/99

4/5/99

70

 

23

Engine Installation

7/1/03

holding

92

12

Canard Wing Installation

4/6/99

3/31/00

29

 

24

Covers and Fairings

5/16/01

3/19/04

149

13

Nose  Section

4/14/99

3/31/00

183

 

25

Finishing

5/11/04

in work

372

 14

Main Spar

4/2/00

5/29/00

99

 

26

Upholstery

---

---

---